UST Remediation LNAPL Multiphase System

A multi­phase extraction system was designed to address an extensive LNAPL plume spanning multiple off-site properties to dewater the upper low-permeability zone and allow product recovery and vapor extraction in the sand units where the NAPL was trapped.

UST Remediation AS/SVE System

An air sparge/soil vapor extraction (AS/SVE) remediation system was designed based on pilot test data. A total of 6 AS wells and 5 SVE wells were installed to remediate gasoline constituents in the groundwater by directly volatilizing the constituents and supplying oxygen for aerobic biodegradation.

E&P Tank Closures

Closures were completed on over 70 produced water holding tanks covering a large area in a remote part of northwestern Colorado. The replacement of the existing culvert pit holding tanks was coordinated with the oil and gas operator to install above-ground tanks with minimal downtime.

Refinery Groundwater Modeling

A groundwater model was developed to address corrective actions under the WDEQ to provide an understanding of remedial alternatives to prevent off-site migration of contaminated groundwater and LNAPL.

Refinery Groundwater Containment System

Air Permitting & Compliance

A containment system was designed under a Consent Order with the WDEQ to prevent off-site migration of contaminated groundwater and LNAPL. An alternative evaluation design was used to select a soil bentonite slurry wall with a series of interceptor.

E&P Groundwater Remediation

Groundwater contamination due to migration from a natural gas well along natural fractures resulted in benzene and methane in surface­ water and groundwater. After several years of operating a sparge system with little progress, Rule was selected to provide remediation for the site.